Case study - Energy efficiency - Ventus Ltd

Ventus Ltd. is located in Hrabrovo village in Dobrich region of Bulgaria. With BEERECL financing, the company installed a wind turbine of 2.0 MW capacity. The average annual wind speed based on on-site measurements is 6.18m/s at a 70 meter height. The expected annual electricity production of the wind farm is 6,014 MWh.

Investment Details:

  • Total Project Cost: EUR 2,812,000
  • KIDSF Grant: EUR 300,000
  • Loan: EUR 2,000,000
  • Simple Payback Period: 5.69 years
  • Internal Rate of Return: over 17,11%

Estimated Annual Figures

  • Annual Electricity Production: 6,014 MWh
  • O&M Costs: EUR 42,500

Project results

  • CO2 emissions reduction